CivilEase / SSC JE Civil 2026
Revise the formula.
Understand the conditions.
Solve the question.
A subject-wise civil engineering formula sheet with units, common mistakes, 30 worked questions and a practical 21-day revision plan.
If you are revising for SSC JE Civil Engineering 2026, use this page to practise formula recall and check the assumptions before substituting numbers. Search a formula, try an original numerical question, then open its worked solution.
This is a selected revision guide, not a complete syllabus or a predicted question paper. All 30 questions are original CivilEase exercises. Use your full course notes and the official syllabus alongside it. The plan assumes you have studied the subjects before.
SSC JE 2026: keep the whole paper in view
The official 2026 notice gives the following standard-duration pattern for a Civil candidate. Eligible candidates may receive additional time under the notice. Check SSC for later amendments, examination dates and candidate instructions.
| Paper | Questions / marks | Time | Wrong answer |
|---|---|---|---|
| Paper I | Reasoning 50 / 50; general awareness 50 / 50; civil & structural engineering 100 / 100 | 2 hours | -0.25 mark |
| Paper II | Civil & structural engineering 100 / 300 | 2 hours | -1 mark |
Source: SSC official 2026 notice, sections 13-14. Do not ignore reasoning and general awareness while revising the technical subjects.
SSC JE Civil Engineering formula sheet
Read each relation together with its units and conditions. Symbols are defined locally: for example, n may refer to porosity in soil mechanics, whereas Manning roughness is written as nM.
Showing all 48 cards.
Mechanics, strength of materials and structures
Direct stress and strain
P = axial force; A = area; delta = change in length; L = original length; E = Young's modulus.
Use carefully: Use Hooke's law only in the linear-elastic range. 1 N/mm2 = 1 MPa.
Poisson's ratio and elastic constants
nu = Poisson's ratio; G = shear modulus; K = bulk modulus.
Use carefully: These modulus relations assume an isotropic linear-elastic material. Keep the minus sign when strains are signed.
Axial elongation and free thermal expansion
alpha = thermal expansion coefficient; Delta T = temperature change.
Use carefully: PL/AE assumes a prismatic member with constant force and E. The thermal expression is for free expansion, not a restrained bar.
Elastic bending and rectangular section
M = bending moment; y = distance from neutral axis; I = second moment of area; Z = section modulus.
Use carefully: b and h are rectangle width and depth, with h in the bending direction. Use elastic beam theory and consistent moment units.
Simply supported beam under full-span UDL
w = load per unit length; L = span; EI = constant flexural rigidity.
Use carefully: Both maxima occur at midspan. This is a full-span uniformly distributed load with simple supports and small deflection.
Euler buckling
Le = effective buckling length; ideal kL: pinned-pinned 1, fixed-free 2, fixed-fixed 0.5, fixed-pinned about 0.699.
Use carefully: Use the weakest bending axis for an ideal slender elastic column. These ideal restraint factors are not a full code design check.
Further reading: MECH.
Concrete, reinforcement and steel quantities
Concrete elastic modulus
Ec and characteristic cube strength fck are in N/mm2 (MPa). Example: M25 gives Ec = 25,000 MPa.
Use carefully: IS 456:2000 educational relation, clause 6.2.3.1. It estimates short-term static modulus, not an exact measured value.
Concrete flexural tensile strength
fcr = estimated flexural tensile strength; fck is in MPa and the result is in MPa.
Use carefully: IS 456:2000, clause 6.2.2. Do not confuse this estimate with direct tensile strength or characteristic compressive strength.
Target mean strength: supplied standard deviation
s = standard deviation in MPa, supplied or established for the concrete production process.
Use carefully: This is the statistical expression for the stated exercise. A full mix design must also check the applicable IS 10262 provisions; do not treat this as the only current requirement.
Singly reinforced rectangular section
fy = steel yield strength; Ast = tension steel area; b = width; d = effective depth.
Use carefully: IS 456 rectangular stress-block assumptions. The steel-yielding expression requires xu not greater than xu,max. With mm and MPa, Mu is N mm.
Development length
phi = bar diameter; sigma s = design stress in the bar; tau bd = design bond stress appropriate to the bar and concrete.
Use carefully: IS 456:2000, clause 26.2.1. Use consistent units and applicable bond-stress adjustments; sigma s is not automatically fy.
Round reinforcing-bar area and mass
Use phi in mm. Area is then mm2. Approximate mass follows from steel density near 7850 kg/m3.
Use carefully: This is a quantity estimate. Add actual lengths, laps, hooks and bends separately; do not apply an arbitrary universal wastage rate.
Code reference: IS 456:2000, clauses 6.2.2, 6.2.3.1, 26.2.1 and rectangular-section stress-block provisions. Consult the applicable code and amendments for design; code tables are not reproduced here.
Soil mechanics and geotechnical engineering
Void ratio and porosity
Vv = void volume; Vs = solid volume; V = total volume.
Use carefully: Enter porosity as a fraction in these relations: 40% means n = 0.40, not 40.
Water content and degree of saturation
Mw = water mass; Ms = dry solid mass; Gs = specific gravity of solids relative to water.
Use carefully: w and Sr must be fractions. For saturated soil Sr = 1, so e = wGs.
Dry and bulk unit weights
gamma d = dry unit weight; gamma = bulk unit weight; gamma w = water unit weight, about 9.81 kN/m3.
Use carefully: Unit weight is force per volume. Do not substitute mass density without a matching conversion.
Effective stress
sigma = total normal stress; u = pore-water pressure; sigma prime = effective normal stress.
Use carefully: This standard relation applies to saturated soil. Positive pore pressure reduces effective stress.
Darcy's law
k = hydraulic conductivity; i = hydraulic gradient; A = total cross-sectional flow area.
Use carefully: Use laminar saturated flow. With k in m/s and A in m2, Q is m3/s. Q/A is Darcy velocity, not seepage velocity.
Rankine active earth pressure
phi prime = effective friction angle; H = retained height; Pa = active force per unit wall length.
Use carefully: Dry cohesionless soil, level backfill, smooth vertical wall, no surcharge or water, and sufficient wall movement to mobilize active conditions.
Fluid mechanics and hydraulics
Hydrostatic pressure
rho = liquid mass density; g = gravitational acceleration; h = vertical depth below a free surface.
Use carefully: This is gauge pressure for a free surface at atmospheric pressure. With SI units, p is Pa.
Continuity
Q = discharge; A = flow area; V = mean velocity across that area.
Use carefully: The two-section equality assumes steady incompressible flow with no intervening inflow or outflow.
Bernoulli with pump, turbine and loss terms
z = elevation; alpha = kinetic-energy correction factor; hp = pump head; ht = turbine head; hL = head loss.
Use carefully: Steady incompressible energy balance. All terms are lengths. Set alpha approximately 1 only when the velocity profile justifies it.
Reynolds number
D = pipe diameter; mu = dynamic viscosity; nu k = kinematic viscosity.
Use carefully: Re is dimensionless. In circular pipe flow, values below about 2000 are commonly classed as laminar; transition is not an exact universal boundary.
Darcy-Weisbach head loss
fD = Darcy friction factor; L = pipe length; D = diameter; V = mean pipe velocity.
Use carefully: Use the Darcy factor, not the Fanning factor: fD = 4 fF. Minor losses require separate terms.
Manning uniform-flow equation
nM = Manning roughness coefficient; Rh = A / wetted perimeter; Sf = energy slope.
Use carefully: This is the SI form. For uniform flow the energy slope equals the bed slope. Do not substitute channel depth for Rh automatically.
Further reading: FLOW.
Hydrology and irrigation engineering
Thiessen-average rainfall
Ai = catchment area represented by gauge i; Pi = rainfall measured by that gauge.
Use carefully: The denominator is total represented area, not the sum of rainfall values. Keep all areas and all rainfall depths in consistent units.
Rational-method peak discharge
For this form, Qp is m3/s, i is mm/h, A is km2 and C is the runoff coefficient.
Use carefully: An approximate small-catchment peak-flow method. Use an intensity tied to the time of concentration and applicable duration; it is not a runoff-volume formula.
Runoff depth to volume
For this form, runoff depth dr is mm, catchment area A is km2, and runoff volume Vr is m3.
Use carefully: Convert rainfall to runoff depth using the stated loss or runoff assumptions first; rainfall depth and runoff depth are not interchangeable.
Duty, base period and delta
Delta = irrigation depth in m; B = base period in days; Du = duty in hectares per m3/s.
Use carefully: Use duty and depth at the same location in the system. Conveyance and application losses cannot be silently ignored.
Application efficiency
Use the same volume units for both water quantities.
Use carefully: Conveyance efficiency instead compares water delivered to the field with water diverted from the source.
Return period and exceedance risk
T = return period in years; N = number of years; R = chance of at least one exceedance.
Use carefully: Assumes independent years and a stationary annual exceedance probability. A 100-year event can occur in consecutive years.
Further reading: RAIN, RUNOFF, IRRIGATION.
Surveying, areas and volumes
Height-of-instrument levelling
HI = instrument height or height of collimation; RL = reduced level; BS = backsight.
Use carefully: A point's reading may be an intermediate sight or foresight. Establish a new HI after moving the instrument.
Levelling arithmetic check
BS and FS sums include all instrument setups along the levelling run.
Use carefully: This checks arithmetic consistency; it does not detect every field error or prove that a benchmark is correct.
Trapezoidal rule for equally spaced offsets
d = common interval; Oi = offset at station i; N = number of intervals.
Use carefully: Use equally spaced offsets for this expression. Area is in m2 when d and offsets are in m.
Simpson's one-third rule
d = common interval; N must be even, so the number of ordinates N + 1 is odd.
Use carefully: Offsets must be equally spaced. Do not force the rule onto a dataset with an odd number of intervals.
Simple circular curve
R = curve radius; Delta c = deflection angle in degrees; Tc = tangent length; Lc = arc length.
Use carefully: This is a simple circular curve without transitions. Use degrees for the displayed arc-length expression.
Prismoidal volume
A1 and A2 = end areas; Am = actual mid-section area; L = separation of end sections.
Use carefully: Exact for a prismoid and an approximation for suitable smoothly changing sections. Am is not automatically the average of the end areas.
Further reading: NUMERICAL.
Environmental engineering
BOD exerted: base-e rate constant
L0 = ultimate first-stage BOD; Yt = BOD exerted in time t; ke = base-e rate constant.
Use carefully: Use consistent time units. If kb is the base-10 constant, ke = 2.303kb; do not interchange the constants.
Hydraulic detention time
V = effective tank volume; Q = volumetric flow rate.
Use carefully: If V is m3 and Q is m3/day, detention time is days. Multiply by 24 to obtain hours.
BOD removal efficiency
Sin and Sout = influent and effluent BOD concentrations, on the same measurement basis.
Use carefully: This concentration-based efficiency assumes comparable flow rates; for unequal flows use mass loads.
Population and water demand
P = population; qc = per-capita demand in litres per person per day; MLD = million litres per day.
Use carefully: This is the demand represented by the supplied qc. Apply leakage, fire demand or peak factors only when the exercise requires them.
Equivalent hardness
Cion = contributing-ion concentration in mg/L; EWion = molecular or atomic weight divided by ionic valence.
Use carefully: Report the result as mg/L as CaCO3. Sum contributing hardness ions, not every ion in the sample.
Surface overflow rate
As = plan area of the settling tank; Q = flow rate.
Use carefully: With Q in m3/day and As in m2, vo is m/day. This is a hydraulic loading measure, not a complete treatment-design criterion.
Further reading: BOD.
Transportation, estimating and project planning
Level-road stopping sight distance: friction model
V = speed in km/h; t = perception-reaction time in seconds; f = longitudinal friction coefficient; SSD is m.
Use carefully: A level-road educational model with constant friction. Use the values stated in the question. Grade or specified deceleration models require different braking terms.
Horizontal curve equilibrium
es = superelevation as a fraction; fs = lateral friction factor; V = km/h; R = m.
Use carefully: This is the point-mass equilibrium approximation, not the separate IRC procedure for allocating superelevation or checking its limits.
Traffic-flow relationship
q = vehicles per hour; k = vehicles per km; v = space-mean speed in km/h.
Use carefully: Use compatible lane and time bases. A speed averaged at one point is not automatically the required space-mean speed.
Time-mean and space-mean speeds
vt = arithmetic mean of speeds observed at a point; vs = harmonic mean for vehicles traversing equal distances.
Use carefully: The harmonic-mean expression requires equal-distance observations. Do not average vehicle speeds arithmetically for a whole equal-distance trip.
Material quantity and item cost
L, B and T = dimensions; rho = mass density; C = cost for the measured item.
Use carefully: Match the density and volume units. Taxes, labour, transport, compaction, deductions and waste are separate assumptions, not hidden constants.
PERT expected activity time
a = optimistic duration; m = most likely duration; b = pessimistic duration, in the same time unit.
Use carefully: These are classical PERT activity estimates. Project duration requires network analysis; do not add durations of parallel paths together.
Further reading: SSD.
30 original SSC JE Civil-style numerical questions
Try each question before opening the solution. Use 45 minutes for an initial diagnostic if appropriate to your level. This is a small learning set, not a full mock or evidence of exam-topic weightage.
Question 01
A steel bar carries an axial tensile load of 60 kN over an area of 300 mm2. What is its direct stress?
- 20 MPa
- 200 MPa
- 2000 MPa
- 0.2 MPa
Show answer and worked solution
Answer: B. 200 MPa
Convert 60 kN to 60,000 N. Stress = 60,000 / 300 = 200 N/mm2 = 200 MPa.
Common mistake: Dividing kN by mm2 without converting force.
Question 02
A prismatic bar has P = 40 kN, L = 2000 mm, A = 400 mm2 and E = 200,000 N/mm2. Find the elastic elongation.
- 0.1 mm
- 10 mm
- 1.0 mm
- 100 mm
Show answer and worked solution
Answer: C. 1.0 mm
Elongation = (40,000 × 2000) / (400 × 200,000) = 1.0 mm.
Common mistake: Mixing a length in metres with area in mm2.
Question 03
An isotropic material has E = 210 GPa and nu = 0.30. What is G?
- 80.77 GPa
- 105 GPa
- 273 GPa
- 161.54 GPa
Show answer and worked solution
Answer: A. 80.77 GPa
G = E / [2(1 + nu)] = 210 / 2.6 = 80.77 GPa.
Common mistake: Using 1 - nu instead of 1 + nu.
Question 04
A simply supported beam spans 6 m and carries a full-span UDL of 12 kN/m. Find its maximum bending moment.
- 18 kN m
- 36 kN m
- 72 kN m
- 54 kN m
Show answer and worked solution
Answer: D. 54 kN m
Mmax = wL2 / 8 = 12 × 6 × 6 / 8 = 54 kN m, at midspan.
Common mistake: Using the cantilever UDL formula for a simply supported beam.
Question 05
A rectangular section is 200 mm wide and 300 mm deep in the bending direction. Find its elastic section modulus.
- 3 × 106 mm3
- 4.5 × 10^8 mm4
- 6 × 106 mm3
- 9 × 106 mm3
Show answer and worked solution
Answer: A. 3 × 106 mm3
Z = bh2 / 6 = 200 × 3002 / 6 = 3,000,000 mm3.
Common mistake: Giving second moment of area I when the question asks for Z.
Question 06
Using the stated IS 456:2000 estimate, find Ec for M25 concrete.
- 5000 MPa
- 125,000 MPa
- 25,000 MPa
- 35,000 MPa
Show answer and worked solution
Answer: C. 25,000 MPa
Ec = 5000 sqrt(25) = 5000 × 5 = 25,000 MPa.
Common mistake: Multiplying by fck instead of its square root.
Question 07
For a statistical exercise, fck = 25 MPa and standard deviation s = 4 MPa. What is fck + 1.65s?
- 29 MPa
- 31.6 MPa
- 41.25 MPa
- 21 MPa
Show answer and worked solution
Answer: B. 31.6 MPa
Target expression = 25 + 1.65 × 4 = 31.6 MPa. This arithmetic alone does not establish all mix-design requirements.
Common mistake: Presenting the statistical expression as a complete mix design.
Question 08
Estimate the mass of a straight 12 mm diameter, 10 m long reinforcing bar using φ2/162 kg/m.
- 0.889 kg
- 12 kg
- 88.9 kg
- 8.89 kg
Show answer and worked solution
Answer: D. 8.89 kg
Mass per metre = 122 / 162 = 0.8889 kg/m. For 10 m, mass = 8.89 kg.
Common mistake: Forgetting to multiply the unit mass by bar length.
Question 09
A 16 mm bar develops a design steel stress of 360 MPa. The already-adjusted design bond stress is 2.4 MPa. Find Ld.
- 600 mm
- 150 mm
- 2400 mm
- 37.5 mm
Show answer and worked solution
Answer: A. 600 mm
Ld = 16 × 360 / (4 × 2.4) = 600 mm. No further bond adjustment is applied because it is already included.
Common mistake: Applying a bar-type adjustment twice.
Question 10
A soil has void ratio e = 0.65. Find porosity.
- 65%
- 39.4%
- 60.6%
- 1.65%
Show answer and worked solution
Answer: B. 39.4%
n = e / (1 + e) = 0.65 / 1.65 = 0.3939, or about 39.4%.
Common mistake: Treating void ratio and porosity as the same quantity.
Question 11
A saturated soil has water content 24% and Gs = 2.65. Find its void ratio.
- 6.36
- 0.24
- 0.636
- 0.0906
Show answer and worked solution
Answer: C. 0.636
For saturated soil Sr = 1, so e = wGs = 0.24 × 2.65 = 0.636.
Common mistake: Entering 24 rather than 0.24.
Question 12
Total normal stress at a saturated-soil point is 180 kPa and pore-water pressure is 55 kPa. Find effective stress.
- 235 kPa
- 55 kPa
- 180 kPa
- 125 kPa
Show answer and worked solution
Answer: D. 125 kPa
Effective stress = total stress - pore pressure = 180 - 55 = 125 kPa.
Common mistake: Adding pore-water pressure.
Question 13
For a saturated laminar-flow specimen, k = 2 × 10-5 m/s, gradient i = 0.4 and total area A = 0.02 m2. Find Q.
- 1.6 × 10-7 m3/s
- 1.6 × 10-5 m3/s
- 4 × 10-7 m3/s
- 8 × 10-6 m3/s
Show answer and worked solution
Answer: A. 1.6 × 10-7 m3/s
Q = kiA = (2 × 10-5) × 0.4 × 0.02 = 1.6 × 10-7 m3/s.
Common mistake: Omitting the area or confusing discharge with velocity.
Question 14
For dry level cohesionless backfill with phi prime = 30 degrees, use the ideal Rankine assumptions to find Ka.
- 3
- 0.5
- 1/3
- 1
Show answer and worked solution
Answer: C. 1/3
sin(30 degrees) = 0.5. Ka = (1 - 0.5) / (1 + 0.5) = 1/3.
Common mistake: Using the passive coefficient instead of the active coefficient.
Question 15
Steady incompressible flow is 0.12 m3/s through a pipe of flow area 0.03 m2. Find mean velocity.
- 0.004 m/s
- 4 m/s
- 0.25 m/s
- 40 m/s
Show answer and worked solution
Answer: B. 4 m/s
V = Q/A = 0.12 / 0.03 = 4 m/s.
Common mistake: Multiplying discharge by area.
Question 16
For a circular pipe, V = 0.5 m/s, D = 0.05 m and kinematic viscosity = 1 × 10-6 m2/s. Find Reynolds number.
- 25
- 250
- 2500
- 25,000
Show answer and worked solution
Answer: D. 25,000
Re = VD / nu k = 0.5 × 0.05 / (1 × 10-6) = 25,000, dimensionless.
Common mistake: Confusing dynamic and kinematic viscosity.
Question 17
Use Darcy friction factor fD = 0.02, L = 100 m, D = 0.2 m, V = 2 m/s and g = 9.81 m/s2. Find major head loss.
- 2.04 m
- 0.51 m
- 4.08 m
- 20.4 m
Show answer and worked solution
Answer: A. 2.04 m
hf = 0.02 × (100 / 0.2) × [22 / (2 × 9.81)] = 2.039 m, or 2.04 m.
Common mistake: Using a Fanning factor in a Darcy-factor equation.
Question 18
A small catchment has C = 0.6, intensity i = 50 mm/h at the relevant duration and area A = 0.8 km2. Estimate rational-method peak flow.
- 0.667 m3/s
- 24 m3/s
- 6.67 m3/s
- 66.7 m3/s
Show answer and worked solution
Answer: C. 6.67 m3/s
Qp = 0.278 × 0.6 × 50 × 0.8 = 6.672 m3/s, or 6.67 m3/s.
Common mistake: Using the km2 coefficient with hectares.
Question 19
Rainfall gauges represent 2, 3 and 5 km2, with rainfall depths 40, 60 and 80 mm respectively. Find Thiessen-average rainfall.
- 60 mm
- 66 mm
- 11 mm
- 660 mm
Show answer and worked solution
Answer: B. 66 mm
Weighted rainfall = (2 × 40 + 3 × 60 + 5 × 80) / (2 + 3 + 5) = 660 / 10 = 66 mm.
Common mistake: Dividing by total rainfall instead of total area.
Question 20
At the same irrigation-system location, base period B = 120 days and duty Du = 1800 ha per m3/s. Find delta.
- 5.76 m
- 0.0576 m
- 15 m
- 0.576 m
Show answer and worked solution
Answer: D. 0.576 m
Delta = 8.64 × 120 / 1800 = 0.576 m = 576 mm.
Common mistake: Reporting metres as millimetres without conversion.
Question 21
A benchmark RL is 100.000 m. Backsight is 1.250 m and a foresight to the next point is 2.100 m. Find that point's RL.
- 99.150 m
- 103.350 m
- 100.850 m
- 98.750 m
Show answer and worked solution
Answer: A. 99.150 m
HI = 100.000 + 1.250 = 101.250 m. RL = 101.250 - 2.100 = 99.150 m.
Common mistake: Adding a foresight instead of subtracting it.
Question 22
Three offsets are 2, 4 and 3 m, separated by two equal 10 m intervals. Find area by the trapezoidal rule.
- 90 m2
- 35 m2
- 65 m2
- 70 m2
Show answer and worked solution
Answer: C. 65 m2
A = 10 × [(2 + 3)/2 + 4] = 10 × 6.5 = 65 m2.
Common mistake: Giving full weights to both end ordinates.
Question 23
For the same three offsets 2, 4 and 3 m at 10 m intervals, find area by Simpson's one-third rule.
- 65 m2
- 70 m2
- 90 m2
- 210 m2
Show answer and worked solution
Answer: B. 70 m2
There are two intervals, so the rule applies. A = (10 / 3) × (2 + 4 × 4 + 3) = 70 m2.
Common mistake: Checking the number of offsets instead of the number of intervals.
Question 24
A tank has effective volume 500 m3 and steady flow 2000 m3/day. Find hydraulic detention time in hours.
- 0.25 h
- 4 h
- 24 h
- 6 h
Show answer and worked solution
Answer: D. 6 h
tH = 500 / 2000 = 0.25 day. In hours, tH = 0.25 × 24 = 6 h.
Common mistake: Leaving the answer in days when hours are requested.
Question 25
Influent BOD is 250 mg/L and effluent BOD is 30 mg/L at approximately equal flow. Find removal efficiency.
- 88%
- 12%
- 83.3%
- 92%
Show answer and worked solution
Answer: A. 88%
Efficiency = 100 × (250 - 30) / 250 = 88%.
Common mistake: Dividing by effluent concentration.
Question 26
Ultimate first-stage BOD L0 = 180 mg/L, base-e rate constant ke = 0.23 per day and t = 5 days. Find exerted BOD.
- 57.0 mg/L
- 180 mg/L
- 123.0 mg/L
- 167.3 mg/L
Show answer and worked solution
Answer: C. 123.0 mg/L
Y5 = 180 × [1 - exp(-0.23 × 5)] = 123.0 mg/L to one decimal place.
Common mistake: Using 10^(-kt) with a rate constant specified for base e.
Question 27
On a level road use speed V = 60 km/h, reaction time t = 2.5 s and longitudinal friction f = 0.35. Find SSD with the displayed friction model.
- 41.7 m
- 82.2 m
- 40.5 m
- 164.4 m
Show answer and worked solution
Answer: B. 82.2 m
Reaction distance = 0.278 × 60 × 2.5 = 41.7 m. Braking distance = 602 / (254 × 0.35) = 40.5 m. Total SSD = 82.2 m.
Common mistake: Calculating only the reaction distance or only the braking distance.
Question 28
Traffic density is 30 vehicles/km and space-mean speed is 50 km/h, on the same lane basis. Find flow.
- 0.6 vehicles/h
- 80 vehicles/h
- 600 vehicles/h
- 1500 vehicles/h
Show answer and worked solution
Answer: D. 1500 vehicles/h
q = kv = 30 × 50 = 1500 vehicles/h.
Common mistake: Mixing per-lane density with all-lane flow.
Question 29
Two vehicles each travel the same road-section length at 30 and 60 km/h. Find their space-mean speed.
- 40 km/h
- 45 km/h
- 90 km/h
- 30 km/h
Show answer and worked solution
Answer: A. 40 km/h
Space-mean speed = 2 / (1/30 + 1/60) = 40 km/h. Their arithmetic time-mean speed would be 45 km/h.
Common mistake: Using the arithmetic mean for equal-distance travel observations.
Question 30
A PERT activity has optimistic duration 2 days, most likely duration 5 days and pessimistic duration 8 days. Find expected duration.
- 4 days
- 6 days
- 5 days
- 15 days
Show answer and worked solution
Answer: C. 5 days
te = (2 + 4 × 5 + 8) / 6 = 30 / 6 = 5 days. Activity variance = [(8 - 2)/6]2 = 1 day2.
Common mistake: Taking an unweighted sum of the three duration estimates.
A practical 21-day SSC JE Civil revision plan
Use this as a flexible revision schedule, not a promise of clearing the exam in three weeks. The subject order is an editorial choice, not a ranking of expected exam marks. Start from your weakest topics if your diagnostic suggests a different order.
Daily starting point: 4 focused hours. Allow about 120 minutes for civil revision and questions, 45 minutes for reasoning, 45 minutes for general awareness, and 30 minutes for formula recall and error-log review. Add breaks separately. On mock days, use 120 minutes for the full paper and redistribute the remaining time to review.
Free SSC JE Civil formula PDF and printable guide
Use Print / Save PDF for an immediate free copy of this page. Choose Save as PDF in your browser. The print view includes formulas, worked solutions and the plan. A compact typeset companion is available through the download button when a PDF download has been added to this post.
Frequently asked questions
Is this the complete SSC JE Civil syllabus?
No. It is a selected revision sheet with 48 formula cards and 30 original numerical exercises. Revise the full official syllabus, including construction materials, steel design, geotechnical topics, reasoning and general awareness. The detailed syllabus is linked below.
Are these SSC previous-year questions?
No. All 30 practice questions were written for CivilEase. They demonstrate the formulas and common mistakes; they are not official SSC questions or predictions of what will appear.
Can I start this 21-day plan from zero?
It is a revision plan for learners who have already studied the subjects. If you are starting from zero, use it as a topic checklist and allow more time for full lessons and guided practice.
Can I use the formulas for real design work?
This is an educational resource. Real projects require current applicable codes, site data, verified inputs and qualified engineering judgement. A short revision formula is not a complete design procedure.
Which units should I use?
Follow the units printed on each card. Some coefficients are unit-specific: 0.278CiA uses intensity in mm/h and area in km2; 8.64B/Du gives irrigation depth in metres. Convert percentages to fractions when a relation requires them.
Sources, code references and scope
The explanations and numerical questions were written for CivilEase. Standard relations are presented with their conditions; the selected public teaching references below support the indicated concepts. No official exam question paper, coaching handout or code table is reproduced.
- Staff Selection Commission: Junior Engineer Examination 2026 noticeSections 13 and 14: exam pattern and indicative syllabus. Check SSC for later amendments and date notices.
- MIT OpenCourseWare: Engineering Mechanics I, Lecture 24Elasticity, signed Poisson relation and elastic beam bending.
- NPTEL IIT Guwahati: Phase Relations of SoilsUse the successive pages for the three-phase system and its definitions.
- NPTEL: Movement of Groundwater, Darcy's LawFlow through saturated porous media and hydraulic-gradient conventions.
- NPTEL IISc: Advanced Foundation Engineering, Earth PressureRankine active pressure, its soil/wall assumptions and the resultant force.
- NPTEL IIT Madras: Hydraulics, uniform-flow formula developmentReynolds number, Darcy-Weisbach factor convention and Manning context.
- NPTEL: Engineering Hydrology, rainfall spatial averagingThiessen polygon weights are gauge-representative area divided by total area.
- NPTEL: Hydrologic Analysis, Rational MethodAssumptions, time-of-concentration context and small-catchment limitations.
- NPTEL IIT Kharagpur: Water requirements and dutyDuty, base period and crop-water requirement definitions.
- NPTEL IIT Kharagpur: Water Quality and Estimation of Organic ContentFirst-stage BOD model and conversion between base-e and base-10 rate constants.
- Federal Highway Administration: The 2001 Green Book changesExplains the older friction SSD form and the move to a deceleration-based form; use the model stated in an exercise.
- NPTEL: Numerical integration, trapezoidal and Simpson rulesNumerical-rule context; the displayed survey forms use equally spaced offsets.
Concrete code references: IS 456:2000 (Plain and Reinforced Concrete - Code of Practice); mix-design requirements must be checked against the applicable IS 10262 edition and amendments. Educational formulas are not substitutes for a full code-based check.

0 Comments