- Lapping is not allowed for the bars having diameters more than 36 mm.
- For dowels rod minimum of 12 mm diameter should be used.
- Longitudinal reinforcement of RCC column not less than 0.8% and more than 6% of gross C/S.
- Minimum bars for a square column is 4 No’s and 6 No’s for a circular column.
- The main bars in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the distributors not less than 8 mm and not more than 1/8 of slab thickness.
- The minimum thickness of slab is 125 mm.
- Dimension tolerance for cubes + 2 mm.
- The freefall of concrete is allowed a maximum of 1.50m.
- Water absorption of bricks should not be more than 15 %.
- pH value of the water should not be less than 6.
- The compressive strength of Bricks is 3.5 N / mm2.
- In steel reinforcement binding wire required is 8 kg per MT.
- In soil filling as per IS code, 3 samples should be taken for core cutting test for every 100m2.
Density of Materials
Material | Density |
Bricks | 1600 – 1920 kg/m3 |
Concrete block | 1920 kg/ m3 |
Reinforced concrete | 2310 – 2700 kg/ m3 |
Curing time of RCC Members for different types of cement
Super Sulphate cement: 7 days
Ordinary Portland cement OPC: 10 days
Minerals & Admixture added cement: 14 days
De-Shuttering time of different RCC Members
RCC Member | De-shuttering time |
For columns, walls, the vertical formworks | 16-24 hrs. |
Soffit formwork to slabs | 3 days (props to be refixed after removal) |
Soffit to beams props | 7 days (props to refixed after removal) |
Beams spanning up to 4.5m | 7 days |
Beams spanning over 4.5m | 14 days |
Arches spanning up to 6m | 14 days |
Arches spanning over 6m | 21 days |
Cube samples required for different quantity of concrete
Quantity of Concrete | No. of cubes required |
1 – 5 m3 | 1 No’s |
6 0 15 m3 | 2 No’s |
16 – 30 m3 | 3 No’s |
31 – 50 m3 | 4 No’s |
Above 50 m3 | 4 + 1 No’s of the addition of each 50 m3 |